Estimates and velocity

Points or hours, how velocity is calculated, and why the first three sprints of a number are meaningless.

4 min read

Points or hours

Taskzin supports story points, hours, or t-shirt sizes mapped to numbers. Points work better for planning because they survive a team member being faster than another; hours work better when you bill for them. Pick one per project and do not mix.

How velocity is calculated

Velocity is the sum of estimates on work completed inside a sprint, averaged over the last three completed sprints. Work carried over counts in the sprint that finished it, not the one that started it.

Give it three sprints

A velocity number from one sprint is noise. After three it is a planning tool. After six it is stable enough that a large deviation is worth asking about rather than worrying about.

Did this answer your question?

If not, write to support and quote this page. Median first reply is under two hours on weekdays.